The evacuation of impounded sediments is one of the most critical aspects associated with reservoirs, with possible drawbacks on the water quality, biodiversity, and ecosystem integrity of downstream river reaches. In this study, the impacts of hydraulic dredging at the Ambiesta Reservoir (Eastern Italian Alps) on the physical habitat and the biological communities (i.e., benthic macroinvertebrates and fish) of the downstream river were assessed by comparing the pre-dredging conditions with data collected on three post-dredging occasions. The dredging operation lasted 68 days and removed an overall sediment volume of 30,600 m(3). During this operation, suspended sediment concentration (SSC) was monitored by turbidimeters and, on average, it was considerably lower than the SSC limit of 1.5 g/L, which exceeded approximately 15% of the overall operation time. Additionally, the dredging operation resulted in negligible deposition of fine sediment on/into the riverbed (0.24-0.7 kg/m(2)). Results for fish and benthic macroinvertebrate communities indicated weak differences in the density (similar to 20% reduction) and diversity of these organisms between pre- and post-dredging sampling occasions. Moreover, the results on the biomonitoring indices based on macroinvertebrates showed a recovery during the last two sampling occasions. Compliance with the SSC limit and avoidance of high SSC peaks, along with limited fine sediment deposition, allowed to successfully mitigate the ecological impacts of this relatively long operation of sediment removal.
Ecological Impact of Hydraulic Dredging from an Alpine Reservoir on the Downstream River
Quadroni, Silvia
Primo
;Crosa, Giuseppe;Servanzi, Livia;Espa, Paolo
2023-01-01
Abstract
The evacuation of impounded sediments is one of the most critical aspects associated with reservoirs, with possible drawbacks on the water quality, biodiversity, and ecosystem integrity of downstream river reaches. In this study, the impacts of hydraulic dredging at the Ambiesta Reservoir (Eastern Italian Alps) on the physical habitat and the biological communities (i.e., benthic macroinvertebrates and fish) of the downstream river were assessed by comparing the pre-dredging conditions with data collected on three post-dredging occasions. The dredging operation lasted 68 days and removed an overall sediment volume of 30,600 m(3). During this operation, suspended sediment concentration (SSC) was monitored by turbidimeters and, on average, it was considerably lower than the SSC limit of 1.5 g/L, which exceeded approximately 15% of the overall operation time. Additionally, the dredging operation resulted in negligible deposition of fine sediment on/into the riverbed (0.24-0.7 kg/m(2)). Results for fish and benthic macroinvertebrate communities indicated weak differences in the density (similar to 20% reduction) and diversity of these organisms between pre- and post-dredging sampling occasions. Moreover, the results on the biomonitoring indices based on macroinvertebrates showed a recovery during the last two sampling occasions. Compliance with the SSC limit and avoidance of high SSC peaks, along with limited fine sediment deposition, allowed to successfully mitigate the ecological impacts of this relatively long operation of sediment removal.File | Dimensione | Formato | |
---|---|---|---|
Quadroni et al 2023_ Sustainability.pdf
accesso aperto
Tipologia:
Versione Editoriale (PDF)
Licenza:
Creative commons
Dimensione
2.67 MB
Formato
Adobe PDF
|
2.67 MB | Adobe PDF | Visualizza/Apri |